Location: Grand Rapids, MN MOD: Construction Manager Contract: $1,550,183   From budget development and permitting to construction and masonry, Rice Lake Construction Group managed all aspects of this new construction project, where we served as both construction manager and masonry contractor. Following completion, we were awarded the 2013 Excellence...

Location: Baxter, MN MOD: Construction Management Contract: $5,428,000 Rice Lake Construction Group served as construction manager for the new 43,000 square foot Dondelinger auto complex. The space consists of two different dealerships, a show room, office space and shop area. As construction manger, we handled budget development, permitting,...

Location: Various MOD: Construction Manager Contract: $100,000 - $1,500,000   As construction manager on multiple Wendy’s restaurant projects, Rice Lake Construction Group’s scope of work included budget development, permitting and overall management of the restaurants’ renovations, from inception through completion. These projects vary from minor facility upgrades, renovations, or...

Location: Nashwauk, MN MOD: General Contracting Contract: $15,687,215 (Unit Price)   Slab on grade and foundation work was performed on a job site spanning approximately 6 miles working simultaneously at each end. The contract was negotiated as a unit price instead of the typical lump sum contract and units included: weight...

Location: Fairmont, MN MOD: General Contracting Contract: $28,401,600 (Hard Bid)   The Fairmont Water Treatment Plant is a new 41,000 square foot water treatment plant located near Budd Lake in Fairmont, MN. The plant can handle up to 5.4 million gallons per day using conventional lime/soda ash softening, sand...

Location: Fort McMurray, Alberta, Canada MOD: General Contracting Contract: $82,000,000 (CAD)   The Canadian Natural Resources Limited Horizon Oil Sands facility expansion project included fabricating, procuring and installing components in the extraction facility. This consisted of installing 49,758 feet of piping, field welds totaling 21,370 diameter inches, pipe shoes,...

Location: Williston, ND MOD: General Contracting Contract: $84,231,000 (Hard Bid)   The Williston Water Resource Recovery Facility is a wastewater treatment plant designed and constructed to treat the wastewater effluent for the city of Williston. Following an initial screening process, oxygenation and liquid/solid separation processes, the plant utilizes an...

Location: Shakopee, MN MOD: General Contracting Contract: $39,527,000   Over 115,000 square feet of concrete make up a Germ Tower and Kiln Tower in the Malt House No. 06 expansion project. Both slip form structures required around-the-clock pours lasting 7 and 10 days respectively. Rice Lake Construction Group self-performed...

Location: Elk River, MN MOD: General Contracting Contract: $16,525,200 (Hard Bid)   This wastewater treatment facility improvement project consisted of constructing a new 4 million gallon aeration basin, RAS/WAS building, operations building and a bio-solids processing building. Also included in the scope of work was the installation of new...

Location: Le Mars, IA MOD: General Contracting Contract: $15,024,000 (Hard Bid)   A new industrial wastewater treatment plant capable of treating 500,000 gallons per day and 14,000 pounds of carbonaceous biochemical oxygen demand was built for the city of Le Mars. The primary purpose of the project was to...