Prior Lake, MN

About This Project

Location: Prior Lake, MN
MOD: General Contracting
Contract: $7,752,600 (Hard Bid)

 

The 14,000 square foot addition to the Shakopee Mdewakanton Sioux Community North Water Treatment Plant allows the plant to produce 1.5 million gallons of water per day. Included in the addition is a 300,000-gallon clear well, a 60,000-gallon reclaim tank, three filters, a reverse osmosis room, and a chemical room. The building envelope was constructed by pouring footings/slab on grade, erecting masonry walls, and placing pre-cast concrete roof planks.

 

Additional project highlights:

  • Well house constructed 1 mile from main site
  • One of three filters for future use
  • All concrete floors stained or epoxy coated
  • Winter construction of 41′ x 60′-4″ clear well with 23′ tall and 1′-4″ thick walls, 1′-10″ base slab and 1′-4″ thick poured in place lid
Category
Water